  • October 2020 Bid package available. https://ranken.edu/ranken-west/rfp-docs-2/
  • October 2020 final floor plan and bid package set
  • September 2020 detailed floor plans and construction documents in progress to get bid set together
  • June 26, 2020 floor plan layout almost complete
  • June 17, 2020 groundbreaking ceremony was held
  • May-June groundwork started