Current Progress

 

  • January 2020 the building should be in full operation.
  • December 2019 the building, now known as the Robert W. Plaster Free Enterprise Center, is complete and micro-enterprises are starting the moving in process.
  • November 2019 Parking lot complete, sidewalks complete. Bathrooms finished. Finishing touches will be happening this month.
  • October 2019 Parking lot and sidewalk installation has started. Painting, tiling, and lots of interior finished in progress.
  • September 2019 Glass windows are installed, garage doors installed, and lots of interior work being done.
  • August 2019 Roof complete. Dirt has been moved off site. Walls and interior work has started.
  • July 2019 Steel is complete. Block walls are complete. Dirt has started moving off site. Roof is almost complete. Siding has started
  • June 2019 Steel is almost complete. Foundation is poured. Block walls in progress.
  • April 2019 Steel is going up
  • March 2019 groundwork almost complete, MEP details underway, steel being delivered
  • February 1, 2019  ground work continues and foundation and piers work underway
  • January 2, 2019 ground work starts
  • September 6, 2018 Construction project kickoff
  • August 29, 2018 L. Keeley Construction awarded construction contract
  • July 27, 2018 Construction bids will be closing
  • July 13, 2018 Demo completed
  • June 28, 2018 Construction bids open
  • June 18, 2018 Construction documents complete
  • April 20, 2018 Construction documents 50% complete
  • April 20, 2018 Demo nears completion
  • April 19, 2018 Final Designs Complete
  • February 26, 2018 Demo Started
  • January 22, 2018 Demo Gears Up!
  • January 10, 2018 Demo Contract Awarded
  • December 18, 2017 A&E Contract Awarded
  • December 11, 2017 Demo IFB’s Close
  • November 20, 2017 Demo IFB’s Open
  • November 15, 2017 A&E RFP’s Close
  • October 11, 2017 A&E RFP’s Open
  • October 6, 2017 Groundbreaking